Number of new homes: 18 two bedroom (4 person) houses (double storey)

Existing plans

Upper Salesbury Drive

Image
Upper Salesbury Dr Existing Site Plan

Lower Salesbury Drive

Image
Lower Salesbury Existing Site Plan
Image
 Greenways Existing Site Plan

Shops Site Existing Site Plan

Image
Shops Site Existing Site Plan

Proposed development plans at consultation stage June 2021

Indicative planning application submission drawings: Spring 2022 to Summer 2022

Timescales

What are we doing

By when

Where we are up to

Garage Development Strategy Cabinet approval

November 2011

Complete

Concept drawings prepared

March 2021

Complete

Billericay Estate Newsletter

18 May 2021

Complete

Notification of S105 Consultation Letter to 175 Secure Tenants

28 May 2021 Complete

Consultation Notice published in Billericay and Wickford Gazette

2 June 2021 Complete

Section 105 Consultation (28 Day Period)

June 2021

Consultation period: 2 June 2021 to 30 June 2021

Issue Section 105 Decision Report post consultation

23 December 2021

Complete

Planning application submissions for each of the four sites

Spring 2022 to Summer 2022