Burrell and Rayner towers

Last updated: 12 August 2024

Next review: 8 August 2025

Pre-commencement works​

  • Fire Engineers and London Fire Brigade carried out independent reviews of building and fire safety design proposals. ​
  • Design works completed in August 2023
  • Building Control reviews and approves the design.
  • Submitted Planning Application for approval in July 2023
  • Carried out consultation process for major works with leaseholders in August/September 2023
  • Estimated to start works in January 2024.

Construction works

  • Scaffolding was erected in January 2024, it will remain in place for the duration of the works.
  • Installation of new fire-rated cavity insulation is currently being installed and should be completed in September 2024.
  • Window replacements with modern compliant materials are ongoing.
  • Carry out mechanical and electrical-related work. For example, the installation of fire alarms, sprinklers and associated infrastructure.
  • Roof replacements are underway.
  • Replace curtain walling system to stairwell with new compliant materials.
  • Fire stopping is continuing.

Works commenced in January 2024 and are due to finish in April 2025.