Burrell and Rayner towers
Last updated: 12 August 2024
Next review: 8 August 2025
Pre-commencement works
- Fire Engineers and London Fire Brigade carried out independent reviews of building and fire safety design proposals.
- Design works completed in August 2023
- Building Control reviews and approves the design.
- Submitted Planning Application for approval in July 2023
- Carried out consultation process for major works with leaseholders in August/September 2023
- Estimated to start works in January 2024.
Construction works
- Scaffolding was erected in January 2024, it will remain in place for the duration of the works.
- Installation of new fire-rated cavity insulation is currently being installed and should be completed in September 2024.
- Window replacements with modern compliant materials are ongoing.
- Carry out mechanical and electrical-related work. For example, the installation of fire alarms, sprinklers and associated infrastructure.
- Roof replacements are underway.
- Replace curtain walling system to stairwell with new compliant materials.
- Fire stopping is continuing.
Works commenced in January 2024 and are due to finish in April 2025.