St Davids Court
Last updated: 13 February 2024
Next review: 13 February 2025
Pre-commencement works
- Fire Engineers and London Fire Brigade carry out independent reviews of building and fire safety design proposals.
- Design works are estimated to be complete in August 2023
- Building Control reviews and approves the design.
- Estimated to start in late September 2023
- Submitted Planning Application for approval in July 2023
- Carry out consultation process for major works with leaseholders in August/September 2023
Construction works
- Carry out mechanical and electrical related works e.g. installation of fire alarms (subject to Fire Engineer’s report)
- Erect scaffold
- Carry out works to the external coating that is compliant with building safety regulations
- Replace balcony soffits with modern compliant materials
- Install Automatic Opening Vents to the head of the stairwell
- Undertake fire upgrade works to the wall between external riser shafts and flats
- Replace windows between flats and internal communal hallways with new fire-rated windows
- Remove scaffold
Estimated start: Late September 2023 and finish April 2025