Pre-commencement works​

  • Fire Engineers and London Fire Brigade carry out independent reviews of building and fire safety design proposals. ​
  • Design works are estimated to be complete in August 2023
  • Building Control reviews and approves the design.
  • Estimated to start in late September 2023
  • Submitted Planning Application for approval in July 2023
  • Carry out consultation process for major works with leaseholders in August/September 2023

Construction works

  • Carry out mechanical and electrical related works e.g. installation of fire alarms (subject to Fire Engineer’s report)
  • Erect scaffold
  • Carry out works to the external coating that is compliant with building safety regulations
  • Replace balcony soffits with modern compliant materials
  • Install Automatic Opening Vents to the head of the stairwell
  • Undertake fire upgrade works to the wall between external riser shafts and flats
  • Replace windows between flats and internal communal hallways with new fire-rated windows
  • Remove scaffold

Estimated start: Late September 2023 and finish April 2025