St Georges Court

Last updated: 9 August 2024

Next review: 9 August 2025

Pre-commencement works​

  • Fire Engineers and London Fire Brigade carry out independent reviews of building and fire safety design proposals
    Estimated to start February 2021 ​and finish April 2021
  • Building Control reviews and approves design works
    Estimated to start April 2021 ​and finish August 2021
  • Carry out consultation process for major works with leaseholders
    Started March 2022 ​and finished April 2022

Construction works 

  • Erect scaffold
    Estimated to start November 2022 and finish January 2023
  • Install new fire rated cavity barriers around penetrations through the external walls
    Estimated to start February 2023 and finish April 2023
  • Replace balcony soffits with modern compliant materials
    Estimated to start February 2023 and finish July 2023
  • Undertake fire upgrade works to wall between external riser shafts and flats
    Estimated to start April 2023 and finish July 2023
  • Carry out works to communal walkways and windows
    Estimated to start April 2023 and finish July 2023
  • Remove and renew cavity wall insulation
    Estimated to start February 2023 and finish April 2023
  • Install smoke detectors in all homes and carry out electrical testing
    Estimated to start October 2024 and finish January 2025
  • Remove scaffolding
    Estimated to start July 2023 and finish August 2023