Northwood Tower

Pre commencement works​

  • Fire engineers and London fire brigade carry out independent reviews of building and fire safety design proposals.
    Estimated to start January 2021​ ​and finish February 2021​
  • Carry out consultation process for major works with leaseholders
    Started March 2022​ ​and finished April 2022​
  • Building Control reviews and approves design
    Estimated to start March 2021​ ​and finish July 2021​

Construction works 

  • Erect scaffold
    Estimated to start August 2022 and finish October 2022
  • Replace balcony soffits with modern compliant materials
    Estimated to start November 2022 and finish February 2023
  • Install new infill panels to external windows to bin chute
    Estimated to start December 2022 and finish February 2023
  • Remove scaffolding
    Estimated to start November 2022 and finish December 2022
  • Carry out mechanical and electrical related works e.g. installation of fire alarms (subject to fire engineer’s report)
    Estimated to start April 2023 and finish September 2023