St Patricks Court
Last updated: 9 August 2024
Next review: 9 August 2025
Pre-commencement works
- Fire Engineers and London Fire Brigade carry out independent reviews of building and fire safety design proposals
Estimated to start January 2021 and finish April 2021 - Building Control reviews and approves design
Estimated to start April 2021 and finish August 2021 - Carry out consultation process for major works with leaseholders
Started March 2022 and finished April 2022
Construction works
- Install new fire rated cavity barriers around penetrations through the external walls
Estimated to start end of January 2023 and finish February 2023 - Replace balcony soffits with modern compliant material
Estimated to start January 2023 and finish May 2023 - Undertake fire upgrade works to wall between external riser shafts and flats
Estimated to start January 2023 and finish May 2023 - Carry out communal walkway and window works
Estimated to start November 2022 and finish April 2023 - Remove and renew cavity wall insulation
Estimated start end of January 2023 and finish May 2023 - Remove scaffolding
Estimated start May 2023 and finish June 2023 - Install smoke detectors in all homes and carry out electrical testing
Estimated to start October 2024 and finish January 2025